Roads Update
Friday 26th September
The deadline for bids for the work is Tuesday 30th September.
The winning bid will be chosen within 7 days
It is anticipated that work will now start around the middle of October
Work will start first on the road by the apartments since it is in the worst condition and the existing road will have to be dug up and new foundations laid.
It is assumed any similar work needed will then be carried out in other parts of Salinas before the full resurfacing starts
We hope to have further information at the end of the 1st week of October
SPOA Committee
Ben Heisterkamp jbch36@hotmail.com
Sara Caetano np88uk@mail.telepac.pt
Chris Bateman chris.bateman@ntlworld.com
The deadline for bids for the work is Tuesday 30th September.
The winning bid will be chosen within 7 days
It is anticipated that work will now start around the middle of October
Work will start first on the road by the apartments since it is in the worst condition and the existing road will have to be dug up and new foundations laid.
It is assumed any similar work needed will then be carried out in other parts of Salinas before the full resurfacing starts
We hope to have further information at the end of the 1st week of October
SPOA Committee